Deploy — Cutover Command Center
Dress Rehearsal 1 • Cutover Window: 48 hours
Cutover Progress
78%
Time Remaining
14h 23m
of 48h window
Tasks Complete
47/61
14 remaining
Blockers
1
Data load running slow
Cutover Tasks — Critical Path
Live✓
System freeze — stop all transports
Raj K.
Basis
Basis
✓
Production database backup
Priya M.
Basis
Basis
✓
Export master data — Bhilai instance
Amit S.
Data
Data
▶
Production data load — Global instance
Amit S.
Data
Data
—
Post-load data reconciliation
Neha R.
Data
Data
—
Smoke test — Finance end-to-end
Vijay P.
FI Lead
FI Lead
—
Smoke test — Supply Chain end-to-end
Deepa K.
MM Lead
MM Lead
—
Fiori launchpad validation
Sanjay T.
Fiori
Fiori
—
GO / NO-GO Decision
Mahesh M.
Tech Lead
Tech Lead
Cutover Intelligence
Data load running 15% slower than estimated. At current rate, completion at 16:45 instead of 15:30. This pushes reconciliation start by 1h 15m. Total cutover will finish within the 48h window but with only 3h buffer instead of 4h 15m.
EY benchmark: In 12 similar cutover dress rehearsals, data load for this volume (2.4TB) averaged 3h 20m. Current pace is within normal range. No escalation needed yet.
Go / No-Go Scorecard
SIT Pass Rate > 95%76%
Zero Critical Defects12 open
UAT Sign-offPending
Data Recon < 0.1%In progress
Cutover Dry Run CompleteRunning
Rollback Plan TestedYes
Hypercare Team ReadyYes
CURRENT VERDICT
NOT READY — 2 of 7 criteria met
This is Dress Rehearsal 1. Production cutover is in 247 days.