Cutover Progress
78%
Time Remaining
14h 23m
of 48h window
Tasks Complete
47/61
14 remaining
Blockers
1
Data load running slow
Cutover Tasks — Critical Path
Live
System freeze — stop all transports
Completed 6h 12m ago • Duration: 15m (Est: 15m)
Raj K.
Basis
Production database backup
Completed 5h 45m ago • Duration: 2h 10m (Est: 2h)
Priya M.
Basis
Export master data — Bhilai instance
Completed 4h 20m ago • Duration: 1h 45m (Est: 1h 30m)
Amit S.
Data
Production data load — Global instance
Running • 64% complete • 2h 15m elapsed (Est: 3h) • ETA: +1h 15m
Amit S.
Data
Post-load data reconciliation
Waiting • Depends on: Production data load • Est: 2h
Neha R.
Data
Smoke test — Finance end-to-end
Waiting • Depends on: Reconciliation • Est: 1h 30m
Vijay P.
FI Lead
Smoke test — Supply Chain end-to-end
Waiting • Depends on: Reconciliation • Est: 1h 30m
Deepa K.
MM Lead
Fiori launchpad validation
Waiting • Depends on: Smoke tests • Est: 45m
Sanjay T.
Fiori
GO / NO-GO Decision
Pending • Requires: All smoke tests passed, reconciliation < 0.1% variance
Mahesh M.
Tech Lead
AI
Cutover Intelligence
!
Data load running 15% slower than estimated. At current rate, completion at 16:45 instead of 15:30. This pushes reconciliation start by 1h 15m. Total cutover will finish within the 48h window but with only 3h buffer instead of 4h 15m.
i
EY benchmark: In 12 similar cutover dress rehearsals, data load for this volume (2.4TB) averaged 3h 20m. Current pace is within normal range. No escalation needed yet.
Go / No-Go Scorecard
SIT Pass Rate > 95%76%
Zero Critical Defects12 open
UAT Sign-offPending
Data Recon < 0.1%In progress
Cutover Dry Run CompleteRunning
Rollback Plan TestedYes
Hypercare Team ReadyYes
CURRENT VERDICT
NOT READY — 2 of 7 criteria met
This is Dress Rehearsal 1. Production cutover is in 247 days.